Project Experience: Lysine Facility Boiler Design and Installation



Background: The client requested ADF's services to design and implement a new 100,000 pound per hour natural gas-fired boiler into their existing steam and condensate process. The equipment will be located in a new pre-engineered metal building that meets insurance requirements and state/local codes and regulations.

Project Summary: This project started in the conceptual phase and went through all phases including start-up and commissioning. Design work took 12 months to complete, with construction lasting an additional six months. A new electrical room was designed to provide service to the new building and additional loads. During the project, ADF:


Project Details